Karawanks Tunnel (motorway)
Overview | |
---|---|
Location | Sankt Jakob im Rosental, Carinthia, Austria/ Hrušica, Jesenice, Slovenia |
Coordinates | 46°31′09″N 14°01′22″E / 46.51917°N 14.02278°E |
Status | Second tube under construction |
Route | Karawanken Autobahn/ A2 motorway |
Operation | |
Work begun | August 1986 / September 2018 |
Opened | June 1991 |
Closed | West-Tube: 2025 - 2027 |
Operator | ASFiNAG / DARS |
Character | Single-tube (Second tube under construction) |
Technical | |
Length | 7,864 m (4.886 mi; 25,801 ft) |
No. of lanes | 2 |
Operating speed | 80 km/h (50 mph) |
The Karawanks Tunnel (German: Karawankentunnel, Slovene: Predor Karavanke or Karavanški predor) is a motorway tunnel crossing the Alpine Karawanks mountain range between Austria and Slovenia, with a total length of 7,864 m (4.886 mi; 25,801 ft), 8,019 m (4.983 mi; 26,309 ft) enclosure between the portals. Its construction began in 1986 and it opened on 1 June 1991. It connects the Austrian Karawanken Autobahn (A11) from Villach with the A2 motorway leading to Kranj and Ljubljana in Slovenia, decongesting the historic Loibl/Ljubelj and Wurzen/Korensko sedlo mountain passes.
History
In the late 1970s it was planned by the Austrian Ministry of Traffic as a two-tube tunnel, (one two-lane tube for each direction), but lower than expected levels of traffic have meant that it has remained a single tube, single lane, two-way tunnel. The tunnel was built between 1986 and 1991 by the Tauern Autobahn stock company, represented by the Austrian state of Carinthia. At its opening it was one of the best equipped tunnels with safety and surveillance systems: emergency phones, fire detectors, video surveillance, traffic signalling, radio and phone connections, air circulation monitoring and carbon monoxide sensors.
Less than a month after its opening, in late June 1991, the Slovene terminus of the tunnel and its border post at Jesenice were briefly seized by an armoured detachment of the Yugoslav People's Army during the Ten-Day War. The site witnessed brief but intense fighting, which included the ferrying of reinforcements to the Yugoslav troops by helicopter and culminated in an ineffectual airstrike by the Yugoslav Air Force. The border checkpoint building was heavily damaged in the crossfire.[citation needed]
Construction of the second tube 2018–2027
Since Slovenia joined the Schengen Area in 2007, border controls have been abolished. Due to increasing traffic volume especially after the completion of the second tube of the Tauern Road Tunnel in June 2011, congestion crops up, especially on weekends in the summer season, and has led to the resumption of plans to build a second tube. The contract for the second twin tunnel was signed in September 2015.
After the construction of a 350-metre-long (1,150 ft) bridge and the extension of the Autobahn, finished on the Austrian side by the end of 2017, the construction of the new tube itself successfully started on 18 September 2018 from the Austrian side.
Construction in Slovenia started a year and a half later in the first week of March 2020 after an award dispute which was resolved in the end of 2019.
Award dispute in Slovenia
The construction in Slovenia was delayed but finally started in the beginning of March 2020 since the national review commission of Slovenia, DKOM,[1] canceled the award of contract made with the Turkish contractor Cengiz Insaat which was initially chosen to build the Slovenian side of the tunnel at the end of November 2018. The reason for this were improper documents submitted for the tender offer to the Slovenian motorway operator DARS[2] in August 2018.[3][4] Additionally DARS decided to reject all offers in general in the midst of February 2019 since all of them had errors according to the motorway company. Six bidders would have been invited to take part in a negotiated procedure with DARS including Cengiz Insaat. The period for objection however ended two weeks later when DARS received two formal objections from the Slovenian construction companies Kolektor CPG and Gorenjska Gradbena. The expert commission from DARS rejected the objections two weeks later handing the decision over to DKOM again.[5]
On 15 May 2019 DKOM published its decision to reject the objections too following the resignation in April of DKOM's chairman Borut Smrdel.[6]
Since then DARS was conducting a negotiated procedure with six applicants and their partners.[7]
The negotiated procedure was once again interrupted from 26 June because Gorenjska construction company and Kolektor CPG lodged an appeal for the third time in a row against the participation of Cengiz İnşaat accusing the company of not being suitable as a contractor. [8][9]
In the mid of July 2019 DKOM decided to reject the appeal from Gorenjska and Kolektor CPG. Right after the publication of the decision DARS published the official offers from the finished negotiated procedure. After two months of evaluation DARS decided to give three tenderers the chance to make a new offer.[10][11][12]
In October 2019 Gorenjska and Kolektor once again lodged an appeal for the fourth time against the new selection of tenderers. DARS rejected it two weeks later as well as DKOM did in November.[13]
Cengiz İnşaat receives the final contract
On 3 December 2019 DARS finally gave a new contract to Cengiz İnşaat worth 98.5 million euros (excl. VAT) after short negotiations with three tenderers.
The appeal period ended without further objections in mid-December 2019.
The winner's chief negotiator, Mehmet Cengiz, subsequently told the media that the contract will be signed in late December. The CEO of Cengiz İnşaat, Utku Gök, said on Monday before the final negotiations that the construction in Slovenia would still be finished in time with his company.[14][15]
Construction in Slovenia finally started in the first week of March 2020. The official contract period for Slovenia started on 2 March 2020. In the meanwhile Austrians have dug 2,400 meters into the mountain by the end of March 2020.
The second tube is set to be finished in June 2025.[16][17] After that, the old tube will undergo intense renovation for two years. Both tubes will finally open 2027.
Tolls
Driving on Austrian as well as on Slovenian motorways requires a toll sticker. However, driving through the tunnel doesn't require any.[18][19] Instead, a special toll (2023 rate) of 8.20 euros[20] (20% VAT included) is imposed on drivers of vehicles up to 3.5 tons for using the tunnel. The toll is collected for the section from the closest on-ramp to the tunnel on the Austrian side to the Austrian/Slovenian border in the middle of the tunnel.[21] The Slovenian vignette is not required as the tunnel is not part of motorway sections with the mandatory use of vignettes.[19] The toll from the Slovenian side is also €8.20.
Vehicles over 3.5t (trucks, buses, motorhomes) pay toll on Austrian highways based on number of kilometres travelled. For the 10 kilometres (6.2 mi) section that includes the tunnel a special rate equivalent to 8.6 times the normal one is applied, coming to 16.27-46.36 € incl. VAT (13.56-38.63 € + 20% VAT)[22] depending on number of axles and engine emission standard. Trucks entering from the Slovenian side pay toll no matter their EURO emission class.[23]
See also
References
- ^ DKOM
- ^ DARS
- ^ "Cengiz Insaat ne bo gradil druge cevi predora Karavanke". Prvi interaktivni multimedijski portal, MMC RTV Slovenija. Retrieved 2018-12-01.
- ^ "Turško podjetje izločeno iz razpisa za gradnjo karavanškega predora". Dnevnik. Retrieved 2018-12-01.
- ^ "Gradnja druge cevi predora Karavanke se spet seli na revizijsko komisijo". RTVSLO.si (in Slovenian). Retrieved 2019-03-25.
- ^ Vrabec, Aljaž (2019-04-03). "FOTO:Odstopil predsednik Borut Smrdel: "Napadov nisem več pripravljen trpeti"". www.delo.si (in Slovenian). Retrieved 2019-06-09.
- ^ "Gorenjski glas | Podaljšan rok za oddajo ponudb za Karavanke". www.gorenjskiglas.si. July 16, 2019. Retrieved 2019-07-17.
- ^ Gole, Nejc (2019-02-15). "Karavanke: Dars zavrnil vse ponudbe in gre v pogajanja z gradbinci". www.delo.si (in Slovenian). Retrieved 2019-07-02.
- ^ "Dars se bo za izgradnjo karavanškega predora pogajal s šestimi ponudniki". RTVSLO.si (in Slovenian). Retrieved 2019-07-02.
- ^ "Na Dars je v novem krogu prispelo pet ponudb za Karavanke, najcenejši spet – pričakovano – turški Cengiz Insaat". Transport in logistika (in Slovenian). Retrieved 2019-08-09.
- ^ "odločitve DKOM - Državna revizijska komisija". www.dkom.si. Retrieved 2019-08-09.
- ^ "Najcenejšo ponudbo za karavanški predor znova podali Turki". RTVSLO.si (in Slovenian). Retrieved 2019-08-09.
- ^ "Dars naj bi zavrnil pritožbi glede predora Karavanke". RTVSLO.si (in Slovenian). Retrieved 2019-12-13.
- ^ "Predor Karavanke: Turki jutri na Darsu pričakujejo dobre novice". Dnevnik. Retrieved 2019-12-13.
- ^ "Vsak dan prvi - 24ur.com". www.24ur.com. Retrieved 2019-12-13.
- ^ "Der Karawankentunnel – das Tor zum Süden".
- ^ "ASFINAG vergibt Neubau der zweiten Röhre Karawankentunnel an ARGE Swietelsky Tunnelbau GMBH & Co KG und Swietelsky Baugesellschaft m.b.H." Archived from the original on 2018-08-17. Retrieved 2018-08-20.
- ^ "Tarife Sondermaut 2016" (in German). ASFiNAG. Retrieved 30 September 2016.
Auf den Sondermautstrecken gibt es keine Vignettenpflicht
- ^ a b "Vignette system". DARS. Retrieved 31 August 2017.
If you drive from Austria through Kravanke tunnel in the direction of central Slovenia, the use of vignette is not mandatory till Hrušica junction. The toll for tunnel Karavanke is valid between first two junctions on the both sides of the state border (junction Hrušica in Slovenia and junction Rosenbach in Austria)
- ^ "Streckenmauttarife". www.asfinag.at (in German). Retrieved 2020-03-04.
- ^ "Special toll rates 2016". ASFiNAG. Archived from the original on 3 October 2016. Retrieved 30 September 2016.
The special toll route is between the St. Jakob im Rosental junction and the national border in the Karawanken Tunnel (Rosenbach toll station)
- ^ "Toll rates 2016". ASFiNAG. Retrieved 2016-09-30.
- ^ "Karavanke tunnel". DARS. Retrieved 31 August 2017.
External links
- Karavanški predor/Karavanke Tunnel. TV-news coverage of the beginning of the construction of the tunnel. August 1986. RTVSLO.
- Karawanks Tunnel. Information about Karawanks Tunnel with Autobahn Webcam (German)
- Karawanks Tunnel. More Information about Karawanks Tunnel (German)